Amaero’s titanium powder plant on schedule
June 28, 2022
Additive Manufacturing parts and service provider Amaero International Limited, headquartered in Notting Hill, Victoria, Australia, has stated that its titanium powder plant is nearing completion, with the supplier of its equipment expected to run an operational hot test in the next few weeks.
Once the hot test is completed, the plant will be disassembled and shipped to the Amaero site in Melbourne to be re-built, commissioned and formally handed over. Once delivered and installed, there will be a Site Acceptance Test to ensure the facility is ready for production.
The design, selection of contractors and required approvals for the site are said to be well underway. The plant is expected to be fully operational in December 2022 and, by the end of that month, should be ready to commence production.